Project Description
Phased development of 4-building hyperscale data center campus totaling 1.2M sq ft on 160 acres. Phase 1 includes two buildings with 80MW critical IT load. Requires backup diesel generation, cooling water system, and new electrical substation. Water usage estimated at 1.5M gallons/day.
Permitting Timetable
Participating Agencies(Subd. 5(a)(1))
Public Meetings(Subd. 5(a)(2))
Statutory Notifications
118 public comments received — significant concern about water appropriation of 1.5M gallons/day. Additional review may be needed.
Decision on need for EIS due by May 1, 2026.
Documents
Permitting Milestones
Quarterly Updates(Subd. 5(b))
CPP prepared ahead of deadline. EAW under review. Significant public interest in water appropriation volumes.
Public comment period complete. 118 comments received. Water usage is primary concern. EIS need decision pending.