Executive Order 26-03 (Feb. 13, 2026): Governor Walz orders permitting overhaul — MPCA directed to reduce review times, increase transparency, and pilot AI tools for environmental permitting. This dashboard supports EO 26-03's transparency and accountability requirements.Read the Executive Order →

← Back to Dashboard

Shakopee Hyperscale Data Center Campus

EAW ReviewData Center·Lead: MPCA·Shakopee, MN
Milestones
4/8
completed
Statutory Deadline
455 days
June 2, 2027
Subd. 6(b): 18-month EAW deadline
Days in Review
140
since CPP request
Timeline Extensions
0%
0 modified milestones

Project Description

Phased development of 4-building hyperscale data center campus totaling 1.2M sq ft on 160 acres. Phase 1 includes two buildings with 80MW critical IT load. Requires backup diesel generation, cooling water system, and new electrical substation. Water usage estimated at 1.5M gallons/day.

Applicant
NorthStar Digital Infrastructure LLC
Estimated Cost
$2,800,000,000
CPP Requested
October 15, 2025
CPP Prepared
December 10, 2025
County
Scott
Requires EIS
No

Permitting Timetable

Today
EAW Submitted
Oct 25
EAW Deemed Complete
Dec 25
CPP Prepared
Dec 25
Public Comment Period
Feb 26
EIS Need Decision
May 26
Air Permit Application
Jun 26
Water Appropriation Permit
Sep 26
Air Permit Issued
Jan 27
Complete
On Track
At Risk
Overdue
Upcoming

Participating Agencies(Subd. 5(a)(1))

MPCAMinnesota Pollution Control Agency
Lead agency for environmental review and air/water permitting
DNRDepartment of Natural Resources
Lead agency for environmental review; water appropriation, mining permits
MDHMinnesota Department of Health
Health impact assessment and drinking water protection
DEEDDepartment of Employment and Economic Development
Economic impact review and workforce development coordination
PUCPublic Utilities Commission
Utility interconnection and rate impact review

Public Meetings(Subd. 5(a)(2))

EAW CommentFebruary 20, 2026
Shakopee Community Center
Public comment meeting on EAW — water usage and air quality focus

Statutory Notifications

High public comment volumeTriggered

118 public comments received — significant concern about water appropriation of 1.5M gallons/day. Additional review may be needed.

Mar 1, 2026
EIS need decision approachingPending

Decision on need for EIS due by May 1, 2026.

Apr 15, 2026Subd. 6(b)

Documents

Environmental Assessment Worksheet
MPCA · Oct 15, 2025
Final
Coordinated Project Plan
MPCA · Dec 10, 2025
Final
Water Usage Impact Assessment
DNR · Jan 20, 2026
Final
Public Comment Summary (118 comments)
MPCA · Mar 15, 2026
Final
Backup Generator Air Emissions Analysis
MPCA · Feb 1, 2026
Under Review

Permitting Milestones

EAW SubmittedComplete
MPCA · Completed Oct 15, 2025
EAW Deemed CompleteComplete
MPCA · Completed Dec 2, 2025
CPP PreparedComplete
MPCA · Completed Dec 10, 2025
Public Comment PeriodComplete
MPCA · Completed Feb 15, 2026
EIS Need DecisionOn Track
MPCA · Target: May 1, 2026
Air Permit ApplicationUpcoming
MPCA · Target: Jun 1, 2026
Water Appropriation PermitUpcoming
DNR · Target: Sep 1, 2026
Air Permit IssuedUpcoming
MPCA · Target: Jan 1, 2027

Quarterly Updates(Subd. 5(b))

Q4 2025December 31, 2025

CPP prepared ahead of deadline. EAW under review. Significant public interest in water appropriation volumes.

Q1 2026March 31, 2026

Public comment period complete. 118 comments received. Water usage is primary concern. EIS need decision pending.