Executive Order 26-03 (Feb. 13, 2026): Governor Walz orders permitting overhaul — MPCA directed to reduce review times, increase transparency, and pilot AI tools for environmental permitting. This dashboard supports EO 26-03's transparency and accountability requirements.Read the Executive Order →

Analytics Overview

Performance metrics across all coordinated project plans

Overall Compliance Rate
95%
milestones on-time or completed
Avg. Review Duration
262
days across all projects
Active Avg.
251
days (in-progress projects)
Complete Avg.
326
days (finished projects)

Milestone Status Breakdown

Completed
37 (61%)
On Track
4 (7%)
At Risk
1 (2%)
Overdue
1 (2%)
Upcoming
18 (30%)
Total: 61 milestones across 7 projects

Agency Deadline Performance

AgencyTotalOn TimeLateRate
MPCA3829176%
DNR2011155%
EQB2000%
MnDOT110100%

Statutory Deadline Comparison

EAW-Only Projects (Subd. 6(b))
277avg. days/ 548 day statutory max (18 months)
5 projects
EIS Projects (Subd. 6(c))
224avg. days/ 1,461 day statutory max (4 years)
2 projects

Review Duration by Sector

Clean Energy489 days avg. (1 project)
Mining354 days avg. (1 project)
Agriculture326 days avg. (1 project)
Manufacturing246 days avg. (1 project)
Municipal184 days avg. (1 project)
Data Center140 days avg. (1 project)
Pipeline93 days avg. (1 project)

Project Timeline Overview

ProjectCPP RequestedCPP PreparedPrep TimeStatutory DeadlineRequires EISExtensions
Iron Range Taconite Processing ExpansionMar 15, 2025May 10, 202556 daysMay 2, 2029Yes5 modified
Mankato Regional Wastewater Treatment UpgradeSep 1, 2025Oct 28, 202557 daysApr 20, 2027NoNone
SunPrairie Solar Panel Manufacturing FacilityNov 1, 2024Dec 20, 202449 daysJun 5, 2026No1 modified
Northern Corridor Natural Gas Pipeline ReplacementDec 1, 2025Jan 28, 202658 daysJan 12, 2030YesNone
Shakopee Hyperscale Data Center CampusOct 15, 2025Dec 10, 202556 daysJun 2, 2027NoNone
Chippewa Valley Ethanol ExpansionJun 1, 2024Jul 28, 202457 daysJan 10, 2026NoNone
Rochester Biomanufacturing CampusJul 1, 2025Aug 25, 202555 daysFeb 12, 2027NoNone

Minnesota vs. Federal FAST-41 Benchmarks

Comparing Minnesota's Coordinated Project Plan performance against federal FAST-41 program outcomes. FAST-41 data from the Federal Permitting Dashboard.

Avg. Time to Decision
Minnesota CPP262 days
FAST-41 Avg.548 days
Pre-FAST-41 Federal Avg.~4.5 years

FAST-41 projects average ~18 months faster ROD times vs. pre-FAST-41

CPP Preparation Time
MN Avg. CPP Prep55 days
Statutory Max60 days
FAST-41 Avg. CPP~90 days

MN statute requires 60-day preparation; federal process typically takes longer

Key Outcomes
Compliance Rate
MN: 95% on-time vs. FAST-41: ~82%
Investment Tracked
MN CPP: $5.8B across 7 projects
FAST-41: $100B+ across 100+ projects
Transparency
Both programs: public dashboards, milestone tracking, quarterly reporting

Annual Permitting Report

Per Subd. 8, the commissioner must report annually on progress toward CPP requirements.