Project Description
Proposed expansion of existing taconite processing facility including new tailings basin, upgraded air emission controls, and increased processing capacity from 8M to 14M tons per year. Project includes 2.4 miles of new haul road and water treatment infrastructure.
Permitting Timetable
Participating Agencies(Subd. 5(a)(1))
Public Meetings(Subd. 5(a)(2))
Deadline Modifications(Subd. 7)
Statutory Notifications
Combined deadline modifications are at 15% of original timeline. If Draft EIS slips further, legislative notification may be required.
Air quality modeling delays may push Draft EIS publication past October 2026 target. Original target: September 2026.
Deadline extended from Jan 15 to Feb 1 due to tribal consultation. Extension within acceptable range.
Q2 2026 quarterly CPP update due by June 30, 2026.
Documents
Permitting Milestones
Quarterly Updates(Subd. 5(b))
CPP prepared and distributed to all participating agencies. EAW review proceeding on schedule.
EIS need decision issued. Scoping process initiated. Tribal consultation commenced with Bois Forte Band.
Draft scoping decision published. Public comment period extended 15 days at request of local communities.
Final scoping decision issued. CPP updated for remainder of EIS process. Air quality baseline monitoring underway.